By Anthony Isaac
The Niger Delta Power Holding Company (NDPHC) has restored 450 megawatts of generation capacity to the national grid following the completion of scheduled maintenance at the Geregu NIPP power plant.
The four-week extended minor inspection, carried out by Siemens Energy, was undertaken to improve the plant’s operational reliability, performance, and efficiency, while extending its Equivalent Operating Hours (EOH) and overall lifespan.
Managing Director/Chief Executive Officer, Engr. Jennifer Adighije, disclosed that in the last one year, NDPHC has successfully recovered six previously dormant gas turbines across its power plants. The recovered units include GT4 at Calabar NIPP, GT1 at Omotosho II, GT1 and GT2 at Benin NIPP, GT4 at Sapele NIPP, and GT3 and GT4 at Alaoji NIPP, which are now on standby for pre-commissioning pending gas supply remedial work.
Collectively, these restored units will contribute an additional 875MW to NDPHC’s mechanically available generation capacity, providing a significant boost to national power supply.
Engr. Adighije also announced the commencement of restoration works on the 225MW Gbarain NIPP plant, which has been idle since 2020. She described the project as a major step toward reviving dormant national generation assets and commercialising the plant’s output to support critical commercial and industrial clusters in the Niger Delta region.
Despite sector-wide challenges, NDPHC has recorded key operational and financial milestones. These include the recovery of 110 containers of critical turbine parts and HRSG components abandoned for over nine years at Onne Port; the rollout of the Light Up Nigeria – Agbara Industrial Cluster project to connect the Agbara Estate to the grid; and a 10MW embedded solar project for an industrial area in Kano. The company has also completed major transmission and distribution projects in Borno and Delta States, as well as the Afam–Ikot Ekpene 330kV double-circuit transmission line.
Other achievements include the recovery of over $10 million in legacy debts from bilateral customers, securing $15 million in insurance claims for the Alaoji plant fire incident, advanced engagements with NERC on recovering NDPHC’s investments in TCN’s transmission expansion projects, and the resolution of longstanding commercial issues with ACCUGAS, resulting in an amended gas supply agreement that reduces government exposure.
To strengthen accountability and staff welfare, NDPHC has introduced a procurement benchmarking desk to streamline procurement processes, Computer-Based Testing (CBT) for improved staff performance management, and a management support allowance to mitigate the impact of fuel subsidy removal.
Engr. Adighije reaffirmed NDPHC’s commitment to “restoring dormant capacity, stabilising operations, and supporting Nigeria’s goal of a more reliable and sustainable power supply value chain.” She added that the company remains dedicated to transparency, accountability, and constructive stakeholder engagement as it works to expand electricity access for businesses and households nationwide.