By Anthony Isaac
The House of Representatives Committee on Power has been informed that the long-delayed 570 megawatts Alaoji Combined Cycle Power Plant in Abia State is now scheduled for completion in the third quarter of 2027.
Managing Director of the Niger Delta Power Holding Company (NDPHC), Engr. Jennifer Adighije, disclosed the new completion timeline on Thursday when members of the committee inspected the project site.
Adighije said the revised schedule followed the adoption of a recovery plan agreed with the contractor after earlier timelines proved unrealistic.

“Initially we had envisaged that the project would be completed by the end of this year, but clearly that is not possible. With the revised schedule, we are now working towards completion by the third quarter of 2027,” she said.
The project, designed to add 570MW to Nigeria’s electricity generation capacity, has suffered delays for over two decades.
Chairman of the House Committee on Power, Rep. Victor Nwokolo, who led the lawmakers on the oversight visit, commended the current leadership of NDPHC for accelerating work on the project.
He said the committee observed improvements in project execution, including the recovery of over 100 containers of equipment required for the power plant.
“Let me start by commending the managing director for being proactive. During the inspection we saw over a hundred containers recovered, which shows extra effort is being put into the system,” Nwokolo said.
According to him, the committee was briefed that substantial equipment purchases had already been made, noting that manufacturing of power sector equipment typically takes several years.
Nwokolo also directed the contractor to ensure that NDPHC management is kept fully informed about equipment procurement and manufacturing progress to avoid further delays.
“We have asked that management should be kept fully informed by the contractor on the purchases they have made so that their team can conduct on-the-spot assessments of the equipment,” he said.
He also urged the contractor to accelerate external works at the site, especially ahead of the rainy season which could slow construction activities.
Despite acknowledging visible progress, the lawmaker stressed that Nigerians ultimately expect the project to translate into improved electricity supply.
“If you know the history of this project, it has taken over 20 years. The present management is living up to expectations, but Nigerians want to see the physical light,” he said.
Nwokolo noted that improved electricity supply to Aba, a major commercial and manufacturing hub, would significantly boost employment and economic activities.
“Aba is a place where you have a lot of self-employment and businesses that require power. By the time this place is completed, the issue of unemployment will be greatly addressed,” he added.
Adighije told the lawmakers that the project had recorded measurable progress since the current management took over.
According to her, the completion level of the project has increased from just over one per cent to about 16 per cent.
She assured the committee that NDPHC is providing both engineering and financial support to ensure the project proceeds without further setbacks.
“In terms of finances, we ensure that we meet our obligations to the contractor. We are not owing the contractor, so there is absolutely no reason to envisage any slippages for now,” she said.
Adighije also thanked President Bola Tinubu for approving the Power Sector Refinancing Plan, noting that improved liquidity in the electricity market would support the completion of ongoing power projects across the country.