The Federal Ministry of Works has intensified efforts to address critical failures along major highways in Delta State, with ongoing remedial and emergency interventions on the Benin–Asaba and Benin–Sapele–Effurun Highways, as well as emergency repair works on the First Niger Bridge.
The interventions aim to restore motorability on distressed sections, improve traffic flow, enhance road safety, and provide immediate relief to motorists and other road users facing difficulties along the affected corridors.
This followed a fresh inspection tour of the affected locations by officials from the Federal Ministry of Works, the Niger Delta Development Commission (NDDC), contractors, and other relevant stakeholders to assess road conditions and monitor the progress of ongoing interventions.
The Federal Controller of Works in Delta State, Engr. Prince Oliseh, who led the Federal Ministry’s delegation, said the interventions were in line with the commitment of the Federal Government, under the leadership of President Bola Ahmed Tinubu and the Honourable Minister of Works, Engr. Sen. David Umahi, to ensure that critical highway infrastructure remains functional, safe and accessible to road users.
Engr. Oliseh noted that the Honourable Minister had continued to place strong emphasis on the prompt rehabilitation of critical sections of the nation’s highways, adding that the interventions in Delta State were already producing visible improvements in traffic movement and road conditions at several locations.
At the First Niger Bridge, the Federal Controller inspected the ongoing emergency repair works being executed by Messrs SKECC Nigeria Limited and noted that the contractor was making steady progress.
The intervention is focused on addressing damaged bridge components and improving the overall serviceability and safety of the bridge. The emergency repair works are scheduled for 7th to September 21.
To facilitate the safe and efficient execution of the repairs, traffic has, in the interim, been diverted to the Second Niger Bridge. Engr. Oliseh appealed to motorists and members of the general public to exercise patience and understanding during the period of the intervention, assuring them that the works are scheduled for completion within the stipulated period, after which normal traffic movement would resume.
The ongoing preparatory works include the scarification of the Asaba- and Onitsha-bound approach lanes and milling of the existing asphalt pavement on the bridge, preparatory to the execution of the required remedial works.
He stated that the ministry was closely monitoring the intervention to ensure compliance with approved specifications and the directives of the Minister of Works.
The inspection team also assessed critical failed sections along the Delta State axis of the Benin–Asaba Highway, where contractors have been directed to intensify remedial activities.Download Interactive Maps
At the Summit Junction–River Niger Bridge Head section, covering approximately 11.5 kilometres, materials mobilised by Hartland Nigeria Limited have started arriving at the site, including hardcore required for the permanent remedial works.