The Federal Government is seeking about $1.2bn in private capital to support its planned 90,000-kilometre nationwide fibre network, with physical deployment expected to begin in October.
The project, known as Project BRIDGE, is being implemented through a newly incorporated company established to drive the nationwide fibre infrastructure programme. Order Demographic Reports
The estimated cost of the project is about $2bn, of which $800m has already been secured through sovereign financing commitments from international development institutions.
The secured financing comprises a $500m World Bank facility approved in October 2025, a $100m loan from the European Bank for Reconstruction and Development (EBRD) approved in February 2026, and a $200m African Development Bank (AfDB) loan approved in April 2026.
The European Union has also provided a €22m grant for Project BRIDGE.
The remaining $1.2bn represents the larger outstanding portion of the project’s estimated capital envelope and is expected to be mobilised through private-sector participation under the project’s public-private partnership structure.
The Strategic Communications Adviser to the Minister of Communications, Innovation and Digital Economy, Osibo Imhoitsike, Friday, confirmed that the government had received a significant private-sector investment offer, with the process currently being concluded.
The Minister of Communications, Innovation and Digital Economy, Bosun Tijani, had in 2024 outlined the government’s plan to develop the nationwide fibre network as part of efforts to expand Nigeria’s digital infrastructure.
According to the government, Project BRIDGE is expected to support broader broadband access and strengthen digital connectivity across the country as deployment moves towards the physical implementation stage.